購買螺旋洗砂機 新設備試機的幾點注意事項/Some points for attention when buying new equipment of spiral sand washing machine

來源: 時間:2018-05-10 16:02:40 次數:

凡是購買螺旋洗砂機的客戶,我們都會在交貨的時候告知客戶,設備安裝完成后一定不要立馬投入產線,生產使用,一定要先進行設備的試機工作,甚至時間允許的情況下,我們的安裝售后人員,會在為客戶安裝完設備后,親自幫其進行試機運行。All the customers who buy the spiral sand washing machine will inform the customers at the time of delivery.

凡是購買螺旋洗砂機的客戶,我們都會在交貨的時候告知客戶,設備安裝完成后一定不要立馬投入產線,生產使用,一定要先進行設備的試機工作,甚至時間允許的情況下,我們的安裝售后人員,會在為客戶安裝完設備后,親自幫其進行試機運行。

我們之所以如此強調新螺旋洗砂機設備的試機工作,是因為新買的設備,雖然我們在出廠時基本能保證設備質量的合格,但是運輸途中的意外或是裝車、檢驗人員的疏忽我們卻難以保證。在螺旋洗砂機設備使用前進行試機,既是對您權益的保證,以方便了今早發現問題,廠家及時的給您解決。那么,關于購買的螺旋洗砂機新設備試機的幾點注意事項,小編給您詳細說一下。

一、當螺旋洗砂機設備的電機啟動后,應該觀察設備是否運轉平衡,設備有沒有不正常的振動,同時,使用專門的工具對電動機的實際功率進行檢測,不能有異常的波動。

二、觀察運行過一段時間后,螺旋洗砂機軸承的溫度是否升高,要求不能超過35度,并且各個密封處不能有粉塵進入。

三、在正式加料試運前,要先進行空負荷運轉,在空負荷運轉良好的基礎上再去進行負荷運轉的試驗。要求空負荷運轉在2至4小時之間,在這過程中觀察各處的連接有沒有松動的情況。

四、負荷運轉試機連續進行5-6個小時,發現沒有異常問題后,新設備的試機才算完成了,螺旋洗砂機才能正式投入工作。

      以上是購買螺旋洗砂機新設備試機的幾點注意事項,購買新設備的客戶朋友請仔細閱讀!

All the customers who buy the spiral sand washing machine will inform the customers at the time of delivery. After the equipment is installed, it must not be put into the production line immediately. It is necessary to carry out the trial operation of the equipment first. Even when time permits, our after-sales installation personnel will help the customers to carry out the trial operation after the equipment is installed.
The reason why we put so much emphasis on the trial operation of the new spiral sand washing machine is that the newly purchased equipment, although we can basically guarantee the quality of the equipment when leaving the factory, is difficult to guarantee the accident during the transportation or the negligence of the loading and inspection personnel. Before the use of the spiral sand washing machine, the trial operation is not only the guarantee of your rights and interests, so as to facilitate the discovery of problems this morning, and the manufacturer will solve them for you in time. Then, about the purchase of the new equipment of the spiral sand washing machine trial several points of attention, small series to you in detail.
I. after the motor of the spiral sand washing machine is started, it shall be observed whether the equipment is running in balance and whether the equipment has abnormal vibration. At the same time, special tools shall be used to detect the actual power of the motor without abnormal fluctuation.
II. Observe whether the temperature of the bearing of the spiral sand washing machine rises after a period of operation. It is required that the temperature shall not exceed 35 degrees, and no dust shall enter into each seal.
III. before the formal feeding test run, it is necessary to run at no load first, and then carry out the load operation test on the basis of good no load operation. It is required to operate at no load for 2 to 4 hours. During this process, observe whether the connection is loose.
IV. the load running test machine shall be continuously operated for 5-6 hours. Only after no abnormal problems are found can the test machine of the new equipment be completed and the spiral sand washing machine be put into operation formally.
The above are some precautions for buying new equipment of spiral sand washing machine, please read it carefully!